Next:

2023-12-20

2023-12-19

  • new relic capability testing, completed platform test
  • bit short day

2023-12-18

  • run 1.26 readiness report
  • retro meeting

2023-12-15

  • complete 1.26 readiness report inc. test cleanup, passing and coverage
  • discuss Cortex BPM idea with Felipe

2023-12-13 and 14: Vacation

2023-12-12: half day

2023-12-11

  • review README for KA
  • watch videos from Richard
  • crtxctl release 0.5.0
  • REOL
    • principles for vendor selection
      • simplify before re-implement
      • reuse thru sub-processes
      • avoid vendor lock in
      • standards based: bpmn, introduce dmn
      • interoperability: oracle to camunda is a problem
        • same users have multiple task lists
        • REST
      • HA
        • dedidated UI workers?
      • open source / low cost
        • support required for 3-4B USD
      • reports
    • workflow video
      • at each milestone: send supplier order
      • escalation if nearing due date may be of interest
      • pattern:
        • pre-process, notification, ‘fix’ loops are common
        • post-notification task is validation (this is PTS code)

2023-12-08

  • capability test convo w AN
  • working on summary table for 1.26 readiness
  • BPM call
    • xp across
    • richard chinn : 22 years on Production Tracking System
      • get rid of oracle workflow in favour of Camunda (TBC)
    • rakesh: started 2007, aw2 sim. to PTS arch (oracle), apollo, now ppe
      • ppe: react + spring boot
      • working w sravan and richard
    • sravan
      • eng lead, started support lead via vtw, apollo
      • 2 years on ppe, 7 tears w els
    • RC:
      • define principle for selection

      • noted tech and lic diffs with 8

      • tempted by SaaS

      • months long human workflow

      • some automation but even then has humans in the loop

      • existing tightly meshed app and workflow

      • desire to extract vetical by vertical

      • predj against vendor lock in, but recognise losing features that way.

      • desire to build own task list

      • next steps

      • install 8 on cortex and get existing workflow onto

      • Rakesh: main reason to move from Alfresco was cost

2023-12-07: office day

  • longish chat about 1.26 report and how to get into advisor:
    • kubent inside inspector? check can run as custom collector
    • refactor remainder as advisor check
    • (A) write up tickets accordingly

2023-12-06: vacation

2023-12-05

per tier, per cluster how much work

2023-12-04

  • callum / camunda

  • self-eval: get started

  • Retro:

    • capability testing as tool to understnd and document
    • too much fire-fighting leaves no time to prevent need for fire-fighting
    • 2024
      • eye candy graphs and ‘forcing’ drives partners
      • integrate advisor / crtxctl / inspector
      • write RFP for desired tool
  • chat with Callum

    • oracle

      • article production
      • issue production
        • more or less as-is should be good enough
      • journal production?
    • proposed: 6 week evalof uncustomised rest API to show how fast progress bpm can deliver.

      • or graphql inserted between rest and react (bit sceptical of this myself: ‘i can write a better api’)

2023-12-01

  • post-creation tasks for rdp-prod and rdp-tooling
  • ppe logging truncation call
  • complete crtxctl publication workflow
  • discuss 1.26 deprecations w FG